Certification of Capability in Business Analysis (CCBA) — Question 330

You are the business analyst for your organization and you're notifying the key stakeholders of a need to gather requirements for an endeavor. One of the stakeholders that you'll need to attend your requirements workshop is the project manager. What role will the project manager have in this workshop?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project manager typically gets involved later in the process, after requirements have been defined, to manage the project execution. Options A and D are incorrect as they suggest active roles in the workshop, which is not appropriate at this stage. Option B, while it implies involvement, does not align with the expected timing of the project manager's participation.