You are the business analyst for your organization and your requirements for the endeavor have recently been approved. Your organization creates a baseline for the requirements based on the approval of the requirements. What must happen in your business analysis activities if the requirements for your endeavor need to be changed?

Answer options

Correct answer: C

Explanation

The correct answer is C because a change control system is essential for managing modifications to requirements in a structured manner. Options A and D suggest creating new baselines and versioning, which are not the primary methods for handling changes. Option B relates to managing configurations but does not directly address the need for systematic change management in requirements.