Certification of Capability in Business Analysis (CCBA) — Question 280
There are five tasks and six inputs to requirements management and communication. As a business analyst, you'll need to gather all of the following inputs for this knowledge area except for which one?
Answer options
- A. Requirement Management Plan
- B. Work breakdown structure
- C. Business Analysis (BA) communication plan
- D. Solution scope
Correct answer: B
Explanation
The correct answer is B, as the Work Breakdown Structure is typically associated with project management rather than specific requirements management. The other options, such as the Requirement Management Plan, BA communication plan, and Solution scope, are essential inputs for effective requirements management and communication.