Certification of Capability in Business Analysis (CCBA) — Question 266
A business analyst (BA) conducted a requirements elicitation session with project stakeholders and communicated the results. The project sponsor expressed concern with certain requirements that address the federal government legislation. What must the BA do to address the concern of the project sponsor?
Answer options
- A. Determine the communication plan for requirements
- B. Compare requirements with compliance requirements
- C. Reassure the project sponsor that testing will be conducted diligently
- D. Ensure requirements are traceable up to user acceptance testing
Correct answer: B
Explanation
The correct answer is B, as it is essential for the BA to ensure that the requirements comply with federal legislation to address the sponsor's concerns. Option A does not directly address compliance issues, C merely offers reassurance without addressing the root of the concern, and D focuses on traceability rather than compliance with legal requirements.