Certification of Capability in Business Analysis (CCBA) — Question 214
A project has experienced several schedule delays. A business analyst (BA) is assigned to the project to help get it back on track. The project manager believes that incomplete requirements are causing the missed milestones. What tool will help address the project manager's concern?
Answer options
- A. Decision analysis
- B. Quality control checklist
- C. Communication plan
- D. Risk review
Correct answer: B
Explanation
The Quality control checklist is instrumental in ensuring that all requirements are met and validated, which addresses the project manager's concern about incomplete requirements. Decision analysis, communication plan, and risk review do not directly focus on validating requirements, thus they are less effective in this scenario.