Certification of Capability in Business Analysis (CCBA) — Question 199

A business analyst (BA) has executed the last planned workshop in a series in order to verify requirements. All issues have been logged in an issues register. What technique is used to manage and resolve the outstanding issues?

Answer options

Correct answer: A

Explanation

The correct answer is A, as item tracking methods are specifically designed to monitor and resolve issues throughout the project lifecycle. The other options, such as metrics and KPIs, focus on measuring performance rather than directly managing issues, while requirements analysis and documentation pertain to gathering and defining requirements rather than resolving logged issues.