Certification of Capability in Business Analysis (CCBA) — Question 182
A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase. What should the business analyst (BA) have done to prevent the delay?
Answer options
- A. Selected a different project methodology
- B. Requested new SMEs participate in the project
- C. Modified the governance structure
- D. Engaged in consistent collaboration
Correct answer: A
Explanation
The correct answer is A because selecting a different project methodology could have allowed for more flexibility and adaptability, which might have kept SMEs engaged throughout the process. The other options, while potentially helpful, do not address the root issue of engagement and collaboration that is critical in a waterfall approach where phases are sequential.