Certification of Capability in Business Analysis (CCBA) — Question 143

A project's business requirements require that the new solution reduce the labor costs currently attributed to performing end of month accounting procedures. Currently the company routinely must pay overtime to meet the deadline. The business analyst (BA) has been documenting the process and wants to ensure that the approach to the process design is feasible for the staff who perform the end of month procedures. Which of the following stakeholders will provide this verification?

Answer options

Correct answer: B

Explanation

The Domain subject matter expert (B) possesses the specific knowledge about the accounting processes and can assess the feasibility of the new design for the staff involved. The other options, such as the Implementation subject matter expert (A) and Project sponsor (D), may not have the detailed operational insights necessary for this verification, while Operational support (C) focuses more on ongoing support rather than process design evaluation.