Before selecting a design solution, a company wants to ensure that stakeholder, solution, and transition requirements align to the business requirements and also that the design satisfies the requirements. What process is the business analyst (BA) completing?
Answer options
- A. Requirements Verification
- B. Requirements Validation
- C. Requirements Engineering
- D. Requirements Elicitation
Correct answer: B
Explanation
The correct answer is B, Requirements Validation, as it focuses on ensuring that the requirements align with business needs and that the design fulfills those requirements. Requirements Verification (A) is about checking if the requirements are correctly implemented, while Requirements Engineering (C) involves the overall process of gathering and defining requirements. Requirements Elicitation (D) is the process of collecting requirements from stakeholders, not validating them.