Certification of Capability in Business Analysis (CCBA) — Question 109
There are many stakeholders that need to be involved in the allocated requirements. One of the stakeholders in the task will be responsible for verifying released and solution components. Which stakeholder has this responsibility?
Answer options
- A. Project team
- B. Project manager
- C. Operational support
- D. Tester
Correct answer: B
Explanation
The Project manager is responsible for overseeing the project and ensuring that all components meet the necessary requirements before release. The Project team may contribute to the process, but it is not their primary duty to validate releases. Operational support typically focuses on maintaining systems post-launch, while the Tester is more involved in the testing phase rather than verifying released components.