Certified Business Analysis Professional (CBAP) — Question 6

You are currently working on creating the activity list for an initiative in your organization. What characteristic must be assigned to each task in your task list?

Answer options

Correct answer: B

Explanation

Each task in the activity list must have a Unique number to ensure it can be distinctly identified. The other options, while important for project management, do not serve the same purpose of providing a unique identifier for tasks.