Certified Business Analysis Professional (CBAP) — Question 53
A business analyst (BA) assigned to a project has been asked to implement regulatory requirements based on priority. What type of traceability relationship can the BA use to find all the solution components that need to be implemented?
Answer options
- A. Validate
- B. Satisfy
- C. Derive
- D. Dependency
Correct answer: B
Explanation
The correct answer, 'Satisfy,' indicates a direct relationship where solution components meet specific regulatory requirements. The other options, while related to traceability, do not directly address the need to ensure that regulatory priorities are met by the solution components.