Certified Business Analysis Professional (CBAP) — Question 459
You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing.
What technique can you use to track problems with the requirements?
Answer options
- A. Problem tracking
- B. Issue tracking
- C. RTM
- D. Baselining
Correct answer: B
Explanation
The correct answer is B, as issue tracking specifically focuses on identifying and managing problems that arise during a project, ensuring they are addressed timely. While problem tracking (A) may seem similar, it is not a recognized formal technique like issue tracking. RTM (C) refers to Requirements Traceability Matrix, and baselining (D) is related to establishing a reference point for project management rather than tracking ongoing issues.