Certified Business Analysis Professional (CBAP) — Question 446
You are the business analyst for your organization and are working on prioritizing requirements.
What plan should guide you through this process?
Answer options
- A. Risk management plan
- B. Project management plan
- C. Requirements management plan
- D. Scope management plan
Correct answer: C
Explanation
The Requirements management plan is designed specifically to outline how requirements will be identified, analyzed, prioritized, and managed throughout the project lifecycle. The other plans—Risk management, Project management, and Scope management—serve different purposes and do not focus specifically on the prioritization of requirements.