You are the business analyst for your organization and are preparing for the conduct elicitation activities. You'll have six inputs as you prepare for this activity.
Which one of the following is not a valid input for the requirements elicitation activity?
Answer options
- A. Requirements management plan
- B. Documented elicitation results
- C. Solution scope
- D. Business need
Correct answer: B
Explanation
The correct answer is B, as documented elicitation results are outcomes of the process rather than inputs needed to conduct the elicitation. The other options, such as the requirements management plan, solution scope, and business need, are essential inputs that guide the elicitation process.