Certified Business Analysis Professional (CBAP) — Question 427

Which of the following inputs of Monitor and Control Risks acquires information from performance measurements and evaluates it to provide variance analysis and forecasting?

Answer options

Correct answer: B

Explanation

The correct answer is B, Work performance information, as it specifically involves analyzing performance data to identify variances and make forecasts. The other options, while related to project management, do not directly pertain to the process of evaluating performance measurements for risk management.