Certified Business Analysis Professional (CBAP) — Question 424
You are currently working on creating the activity list for an initiative in your organization.
What characteristic must be assigned to each task in your task list?
Answer options
- A. Procurement needs
- B. Roles and responsibilities
- C. Unique number
- D. Risk level
Correct answer: C
Explanation
Each task in a task list must have a unique number to ensure easy identification and tracking throughout the project lifecycle. The other options, while important, do not serve the specific purpose of uniquely identifying each task, which is essential for organization and management.