You are the business analyst for THY Organization and you have gathered the requirements. You have presented the requirements to the stakeholders and they have approved your requirements.
You are now working with Francie on recording the dependencies and relationships for each of the requirements.
Why would you want to record the dependencies and relationships for the requirements?
Answer options
- A. To help determine the sequence in which requirements are to be addressed.
- B. To help determine which requirements carry the most risk.
- C. To help determine the total cost for the solution to be implemented.
- D. To help determine the total time for the solution to be implemented.
Correct answer: A
Explanation
Recording the dependencies and relationships among requirements is crucial for understanding the order in which they should be addressed, which is why option A is correct. Options B, C, and D, while important, do not directly relate to the need for determining the sequence of addressing the requirements.