Certified Business Analysis Professional (CBAP) — Question 383

Which of the following processes is must at the end of each project phase to determine the completeness of the project work and to gain the customer's acceptance to move the project forward?

Answer options

Correct answer: D

Explanation

The correct answer is D, as a Phase gate review is specifically designed to evaluate the project's progress and ensure that all requirements are met before moving forward. Options A, B, and C are important processes, but they do not specifically focus on obtaining customer acceptance or determining project phase completion in the same way that a Phase gate review does.