Certified Business Analysis Professional (CBAP) — Question 378
Your organization uses the MoSCoW approach to requirements prioritization.
What does MoSCoW mean?
Answer options
- A. Must, Should, Could, Would
- B. Must, Should, Could, Won't
- C. Mission, Schedule, Cost, Willingness
- D. Must not, Should not, Could not, Will not
Correct answer: B
Explanation
The correct answer is B: Must, Should, Could, Won't, which accurately reflects the categories used in the MoSCoW prioritization technique. Option A incorrectly includes 'Would' instead of 'Won't', while options C and D provide entirely different phrases that do not represent the MoSCoW framework.