Certified Business Analysis Professional (CBAP) — Question 355
What plan will describe the stakeholder groups, communication needs, and the level of formality that is appropriate for the requirements?
Answer options
- A. Requirements management plan
- B. Project management plan
- C. Scope management plan
- D. Business analysis communication plan
Correct answer: D
Explanation
The correct answer is D, as the Business analysis communication plan specifically addresses stakeholder communication needs and the appropriate level of formality. The other options, while related to project management, do not focus specifically on the communication aspects for requirements gathering.