Certified Business Analysis Professional (CBAP) — Question 351

Which of the following reports is generated whenever the project is slipping off the project schedule and includes an explanation of the problem?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Schedule variance report, as it specifically details discrepancies in the project timeline. The other options, such as A (Status report) and D (Cost variance report), do not focus exclusively on schedule issues, while C (Delay report) is not a standard term used in project management reporting.