Certified Business Analysis Professional (CBAP) — Question 340
Which of the following is the process of analyzing the areas of a project that are most affected by risk?
Answer options
- A. Risk Identification
- B. Risk Urgency Assessment
- C. Risk Categorization
- D. Risk Analysis
Correct answer: D
Explanation
The correct answer is D, Risk Analysis, as it specifically involves assessing the impact of risks on various project areas. Options A, B, and C refer to different aspects of risk management, such as identifying risks, assessing their urgency, and categorizing them, but do not focus on the analysis of their effects.