Certified Business Analysis Professional (CBAP) — Question 336

Which of the following is a process of adding labor to a project to reduce the project duration?

Answer options

Correct answer: D

Explanation

The correct answer is D, Crashing, which refers to the technique of adding resources to accelerate project completion. Options A, B, and C do not relate to this process; Forming and Storming are stages in team development, while Rolling wave planning is a project management technique for planning and scheduling.