Certified Business Analysis Professional (CBAP) — Question 336
Which of the following is a process of adding labor to a project to reduce the project duration?
Answer options
- A. Forming
- B. Storming
- C. Rolling wave planning
- D. Crashing
Correct answer: D
Explanation
The correct answer is D, Crashing, which refers to the technique of adding resources to accelerate project completion. Options A, B, and C do not relate to this process; Forming and Storming are stages in team development, while Rolling wave planning is a project management technique for planning and scheduling.