Certified Business Analysis Professional (CBAP) — Question 333
Which of the following document is created first after project is awarded and statement of work is handed over to the project manager?
Answer options
- A. Work breakdown structure (WBS)
- B. WBS dictionary
- C. Project scope statement
- D. Project charter
Correct answer: D
Explanation
The Project Charter is the initial document created after a project is awarded, outlining the project's objectives and stakeholders. The Work Breakdown Structure (WBS), WBS dictionary, and Project scope statement are developed later in the project planning phase and depend on the details established in the Project Charter.