Certified Business Analysis Professional (CBAP) — Question 331
Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?
Answer options
- A. Pie chart
- B. Pareto Chat
- C. Critical Path Method
- D. Scatter chart
Correct answer: C
Explanation
The Critical Path Method (CPM) is the most suitable choice for upper management as it clearly outlines the timeline and critical tasks of a project, enabling informed decision-making. In contrast, pie charts, Pareto charts, and scatter charts do not provide the comprehensive overview of project timelines and dependencies that CPM offers.