Certified Business Analysis Professional (CBAP) — Question 312
Management would like you to front-load the requirements with the most risk requirements.
Why would management prefer the risky requirements first in the prioritization?
Answer options
- A. So if the risk comes true the project will fail will little investment in the work.
- B. So if the risk comes true then the project manager can mitigate the risk event.
- C. So if the risk comes true they'll receive the reward as soon as possible.
- D. So if the risk comes true then there's ample time to correct the problem.
Correct answer: A
Explanation
The correct answer, A, indicates that prioritizing risky requirements allows the project to fail early with less investment if the risks materialize, minimizing potential losses. Option B is incorrect because it doesn't directly address the prioritization of risky requirements, while C and D focus on benefits and time management, which are not the primary concerns in risk management.