Certified Business Analysis Professional (CBAP) — Question 295
Some of the requirements in the solution must be completed because of laws and regulations in your industry. Management would like you, the business analyst, to rank the requirements according to the relevant laws.
What type of requirements prioritization is management having you complete?
Answer options
- A. Regulatory ranking
- B. Business value ranking
- C. Constraint ranking
- D. Risk ranking
Correct answer: A
Explanation
The correct answer is A, Regulatory ranking, as it specifically pertains to organizing requirements based on legal and regulatory obligations. The other options do not focus on laws: B relates to the value of the requirements to the business, C involves limitations on the project, and D concerns potential risks associated with the requirements.