Certified Business Analysis Professional (CBAP) — Question 284
Which of the following authorizes the project to exist within the organization?
Answer options
- A. Project charter
- B. Project network diagram
- C. Project integration management
- D. Project boundaries
Correct answer: A
Explanation
The correct answer is A, the Project charter, as it formally authorizes the existence of the project. The Project network diagram (B) is used for scheduling and planning, Project integration management (C) focuses on ensuring that project components work together, and Project boundaries (D) define the limits of the project but do not authorize its existence.