Certified Business Analysis Professional (CBAP) — Question 270
Which of the following is a visual decomposition of the project scope?
Answer options
- A. Budgeted Cost of Work Scheduled (BCWS)
- B. Resource Breakdown Structure (RBS)
- C. product breakdown structure (PBS)
- D. Work Breakdown Structure (WBS)
Correct answer: D
Explanation
The Work Breakdown Structure (WBS) is the correct answer because it provides a hierarchical decomposition of the project scope into manageable sections. The other options, while related to project management, do not serve as a visual representation of the project scope; BCWS is a cost measurement, RBS focuses on resources, and PBS is specific to product components.