Certified Business Analysis Professional (CBAP) — Question 241

You are the business analyst for your organization and preparing to complete the requirements elicitation activities. Your manager wants to know when the requirements elicitation process will be completed.
Which of the following responses best describes the nature of the requirements elicitation process?

Answer options

Correct answer: D

Explanation

The correct answer is D because requirements elicitation is an ongoing process that integrates throughout the project rather than being a single, isolated phase. Option A suggests a rigid timeline based on project scheduling, while B incorrectly attributes duration solely to stakeholder willingness. Option C implies that project size alone dictates duration, which is not accurate.