Certified Business Analysis Professional (CBAP) — Question 212

A business analyst (BA) has recently completed a comprehensive stakeholder analysis. Next, the BA would like to consider ways in which to ensure that the stakeholders remain engaged throughout the change strategy. Some of the considerations include timing and frequency, location, available tools, delivery methods, and the stakeholders' preferences. In which of the following plans would the BA document these considerations?

Answer options

Correct answer: D

Explanation

The correct answer is D, as the Stakeholder Collaboration Plan specifically focuses on how to engage stakeholders effectively throughout the change strategy. The other options do not address the engagement aspect as comprehensively; for instance, the Communications Management Plan (A) primarily deals with communication strategies rather than ongoing stakeholder involvement.