Certified Business Analysis Professional (CBAP) — Question 198
During a requirements review, the implementation subject matter expert (SME) identified the requirement 'parsing of data' that must be implemented before other requirements. The business analyst (BA) has given this requirement high priority.
What factor influenced the prioritization of the requirement?
Answer options
- A. Data Dictionary
- B. Constraint
- C. Dependencies
- D. Risk
Correct answer: C
Explanation
The correct answer is C, Dependencies, because the requirement for 'parsing of data' is essential for fulfilling other requirements that rely on it. The other options do not accurately reflect the reason for prioritization in this context; for instance, a Data Dictionary provides definitions but does not influence order, while Constraints and Risks do not imply a direct dependency for implementation.