Certified Business Analysis Professional (CBAP) — Question 196

An online stock trading system is under implementation.
Which of the following events can be considered as a trigger for re-prioritization?

Answer options

Correct answer: C

Explanation

The correct answer is C because uncovering further dependencies among solution components indicates that the current plan may need adjustment to ensure successful integration. Options A and B, while important, do not directly affect project priorities in the same way. Option D, although concerning quality, relates more to defects than to the prioritization of project tasks.