Certified Business Analysis Professional (CBAP) — Question 196
An online stock trading system is under implementation.
Which of the following events can be considered as a trigger for re-prioritization?
Answer options
- A. A team member has left the project and is being replaced
- B. A new initial public offering in the stock market is introduced
- C. Further dependencies among solution components are uncovered
- D. Number of reported quality defects is growing through phases
Correct answer: C
Explanation
The correct answer is C because uncovering further dependencies among solution components indicates that the current plan may need adjustment to ensure successful integration. Options A and B, while important, do not directly affect project priorities in the same way. Option D, although concerning quality, relates more to defects than to the prioritization of project tasks.