Certified Business Analysis Professional (CBAP) — Question 187
You are the business analyst for your organization. You are identifying new opportunities to improve upon your existing web services. Management is open to new opportunities as long as the changes do not take more than 60 days to implement.
What type of a factor does the 60 day implementation represent?
Answer options
- A. Technical constraint
- B. Schedule constraint
- C. Business constraint
- D. Assumption
Correct answer: C
Explanation
The 60-day implementation timeline is a limitation imposed by the organization on its operations, categorizing it as a business constraint. While it does have scheduling implications, the core of the restriction is rooted in business priorities, unlike technical constraints which relate to technology issues or assumptions that are not verified.