Certified Business Analysis Professional (CBAP) — Question 158

You are the business analyst for your organization and are currently with several key stakeholders as part of the determination of which business analysis approach is most appropriate for the current project.
Which one of the following is not a stakeholder that is considered when completing the business analysis planning and monitoring task to determine a business analysis approach?

Answer options

Correct answer: D

Explanation

The correct answer is D, as functional management is typically not directly involved in the business analysis planning and monitoring tasks. In contrast, testers, project managers, and regulators play crucial roles in providing insights and requirements for the analysis approach.