Which of the following is an estimate based on past projects to predict the current cost and/or duration of the current project?
Answer options
- A. Current estimate
- B. Past project cost
- C. Past estimate
- D. Top-down estimate
Correct answer: D
Explanation
The correct answer, D, refers to a top-down estimate which utilizes the data from earlier projects to provide a forecast for the present one. Options A and C do not specifically relate to the practice of estimating based on historical data, while B pertains more to the costs of past projects rather than an estimate for the current project.