Certified Business Analysis Professional (CBAP) — Question 146
The project manager wants to have the requirements analysis phase approved and asks the business analyst (BA) if this is possible. The BA wants to ensure that the requirements package is complete prior to closing the analysis phase. What would help the BA expedite the approval process for the analysis phase?
Answer options
- A. Solution performance measures
- B. Business analysis information architecture
- C. Solution functional capabilities
- D. Business analysis approach
Correct answer: B
Explanation
The correct answer, B, Business analysis information architecture, provides a structured way to present and organize the requirements, making it easier for stakeholders to understand and approve them. The other options, while relevant to the project, do not directly facilitate the approval process in the same way that a well-defined information architecture does.