Certified Business Analysis Professional (CBAP) — Question 137
Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?
Answer options
- A. Project manager
- B. Subject matter expert
- C. Solution owner
- D. Stakeholder
Correct answer: C
Explanation
The Solution owner is the one who oversees the project's deliverables and is responsible for key approvals related to the project scope and its success. The Project manager typically manages the execution but does not have the final say on scope approvals. Subject matter experts provide insights but do not approve project elements. Stakeholders have an interest in the project but do not directly approve the specified project components.