Certified Business Analysis Professional (CBAP) — Question 107
In a software implementation project, the designated business analyst (BA) has conducted all the elicitation activities and now needs to confirm the elicitation results.
What is used by the BA Professional to guide which sources of information and which results are to be compared?
Answer options
- A. Information management approach
- B. Business analysis plan
- C. Elicitation activity plan
- D. Business analysis approach
Correct answer: C
Explanation
The correct answer is C, the Elicitation activity plan, as it specifically outlines the methods and sources to be used for gathering and validating results. The other options, while related to business analysis, do not directly guide the BA in comparing elicitation results against information sources.