An organization finalized a contract in which a vendor is expected to design, procure, and construct a power substation for $3,000,000. In this scenario, the organization agreed to which of the following types of contracts?
Answer options
- A. A cost-reimbursable contract.
- B. A lump-sum contract.
- C. A time and material contract.
- D. A bilateral contract.
Correct answer: B
Explanation
The correct answer is B, a lump-sum contract, because it specifies a fixed price for the entire project. The other options are incorrect as a cost-reimbursable contract involves variable costs, a time and material contract charges based on time spent and materials used, and a bilateral contract refers to an agreement between two parties but does not specify pricing structure.