Certified Internal Auditor (CIA) Part 3: Business Knowledge for Internal Auditing — Question 200
The project charter is an output from which of the following?
Answer options
- A. Scope planning
- B. Scope definition
- C. Scope verification
- D. Project initiation
Correct answer: D
Explanation
The project charter is created during the Project initiation phase, which is crucial for formally starting the project and defining its objectives. The other options relate to different aspects of project scope management, but they do not directly produce the project charter.