Certified Internal Auditor (CIA) Part 3: Business Knowledge for Internal Auditing — Question 163
An organization upgraded to a new accounting software. Which of the following activities should be performed by the IT software vendor immediately following the upgrade?
Answer options
- A. Market analysis to identify trends.
- B. Services to manage and maintain the IT infrastructure.
- C. Backup and restoration.
- D. Software testing and validation
Correct answer: D
Explanation
The correct answer is D because software testing and validation are crucial immediately after an upgrade to ensure that the new system functions correctly and meets requirements. Options A, B, and C focus on activities that are not immediate priorities following a software upgrade.