Certified Internal Auditor (CIA) Part 2: Practice of Internal Auditing — Question 43

An organization has adopted an enterprise-wide risk management process and has appointed a chief risk officer (CRO) to manage the process. The board has requested that the audit committee have oversight over the risk management function. Which of the following statements is not true regarding this situation?

Answer options

Correct answer: A

Explanation

The correct answer is A because the audit committee should indeed receive assurance from the CRO about the risk management process. Statement B is true as the chief audit executive does have the authority to conduct risk assessments. Statement C is accurate as the audit committee does hold overall responsibility for risk management on behalf of the board, and statement D is also true since senior management is accountable for internal controls to the board.