Certified Internal Auditor (CIA) Part 2: Practice of Internal Auditing — Question 193

The engagement supervisor would like to change the audit program's scope prior to beginning fieldwork. According to IIA guidance, before any change is implemented, what is the most important action that should be undertaken?

Answer options

Correct answer: D

Explanation

The correct answer is D because obtaining approval from the chief audit executive is essential to ensure that any changes to the audit scope are sanctioned at a high level. Options A, B, and C, while important, are secondary steps that should follow after the necessary approval has been secured.