Certified Internal Auditor (CIA) Part 2: Practice of Internal Auditing — Question 175

While performing fieldwork for an assurance engagement, a member of the internal audit team identified a key control that was not identified during the planning phase of the engagement. Which of the following actions by the internal auditor would be most appropriate?

Answer options

Correct answer: A

Explanation

The correct answer is A because promptly adjusting the audit work program ensures that the newly identified control is tested without delay, maintaining the integrity of the audit process. Options B and D delay addressing the control, which could lead to oversight, while option C unnecessarily requires supervisor approval for a timely adjustment that should be made by the auditor.