Certified Internal Auditor (CIA) Part 1: Business Acumen — Question 84

A manufacturing organization receives all direct materials for finished goods production. Which of the following is the strongest preventive control for lapses in quality assurance?

Answer options

Correct answer: D

Explanation

The correct answer is D because manually inspecting received supplier materials helps ensure that only high-quality inputs are used in production, preventing potential quality issues. Options A and C focus on post-production processes, which do not prevent quality lapses, while B relates to measurement but does not address the quality of incoming materials specifically.