IBM FileNet Content Manager V5.5 — Question 9
If EXPINTERVAL 12 has been set in the dsmserv.opt configuration file when is the first time the expire inventory process starts?
Answer options
- A. 12 hours after the start of the IBM Spectrum Prefect Server
- B. 12 hours after a database backup
- C. at 12 PM in the UTC timezone
- D. directly after the start of the IBM Spectrum Prefect Server
Correct answer: B
Explanation
The correct answer is B because the expire inventory process is scheduled to run 12 hours after a database backup is completed. Options A and D incorrectly relate the process to the server's start time, while option C references a specific time rather than an event related to backups.