IBM Tivoli Monitoring V6.3 Implementation — Question 93
The job plan coordinator needs to add new tasks to an existing job plan which is currently revision 2. The coordinator selects Revise Job Plan from the More
Actions menu and now has a new job plan version, revision 3. What is the status of revision 2?
Answer options
- A. ACTIVE
- B. PNDREV
- C. REVISED
- D. INACTIVE
Correct answer: C
Explanation
The correct answer is C, REVISED, because when a new revision is created, the previous version is marked as revised. The other options do not accurately reflect the status of a job plan that has been modified to create a new version.