IBM Tivoli Monitoring V6.3 Implementation — Question 73

The planner identified that the pump required four widgets as material on the work plan. An electrician was issued a quantity of four widgets from the storeroom and was able to complete the work using only two of the four widgets. The two unused widgets were recorded as returned.
How would this be reflected on the Actuals Tab of the Work Order?

Answer options

Correct answer: D

Explanation

The correct answer is D because the transaction involves both issuing and returning widgets. The electrician issued four widgets but returned two, necessitating separate entries for both the issue and the return. The other options are incorrect as they fail to capture both transactions appropriately.